Projects

Acidic Grassland Soil pH Treatment – Swansea Road, Merthyr

The Challenge

Newly applied topsoil at a development on Swansea Road, Merthyr had recorded a near-neutral pH of 6.95, which no longer complied with the acidic grassland landscaping strategy for the site. The issue needed to be addressed before establishment of the specified acidic grassland habitat, with seedlings already being grown on for planting. The treatment therefore had to alter the soil chemistry progressively while achieving consistent coverage across the target areas. Much of the treatment area was located on raised ground to the north and east of the site, including steep slopes where conventional application methods would have been less efficient. The combination of programme pressure, sloping terrain and the need for a controlled application made the works both technically specific and time-sensitive. Swansea Road Details

Our Solution

EcoVigour proposed elemental sulphur as the soil amendment to progressively reduce pH and move conditions towards the range required for acidic grassland establishment. Once incorporated into the soil environment, bacteria oxidise elemental sulphur to form sulphuric acid, gradually increasing soil acidity rather than creating an immediate short-lived adjustment. Micro-pill elemental sulphur was selected and applied at a specified rate of 50 g/m². To achieve practical, even distribution over the sloping ground, the sulphur was combined with mulch and tackifier and delivered through a hydroseeder. Hand application by spray was retained for sensitive or difficult-to-reach sections so that the treatment could be extended beyond areas readily accessible from the main spraying position.

Delivery & Techniques

The treatment mix of micro-pill elemental sulphur, mulch and tackifier was prepared in the hydroseeder and sprayed evenly across the designated areas on the raised northern and eastern parts of the site. Hydroseeding provided an efficient means of distributing the specified treatment rate over broad, steep and irregular ground while the mulch and tackifier helped retain the applied material on the soil surface. Operatives used hand spraying where access, slope geometry or surrounding features made the main application less suitable, allowing coverage to be controlled at close range. The photographs show the treatment applied across the exposed slope, with the coloured hydroseeding matrix providing a clear visual indication of coverage during the works. The full application was completed in a single day, demonstrating EcoVigour’s ability to mobilise specialist hydroseeding equipment and deliver targeted soil treatment efficiently.

Outcomes & Benefits

EcoVigour completed the specified sulphur treatment across the target areas in one day, allowing the landscaping programme to progress without a prolonged soil-treatment operation. The application established the first stage of a managed process to lower the recorded pH from 6.95 towards conditions suitable for the proposed acidic grassland. Follow-up pH monitoring is planned at intervals of several months to measure the response of the soil and determine whether, and when, further applications are required. This monitoring-led approach avoids claiming an immediate pH result before the elemental sulphur has had time to oxidise and allows subsequent treatment to be based on measured site conditions. The project demonstrates EcoVigour’s ability to combine specialist hydroseeding equipment with practical environmental knowledge to deliver precise, site-specific treatment using directly operated plant and skilled teams.

Need help with Something Similar?

Leave your details here and we’ll get back to you as soon as possible. Alternatively, feel free to call us, drop an email or swing by the office any time.

08448 400 401

info@ecovigour.com

Hardwick Farm Five Lanes, Caerwent, Newport, Monmouthshire, NP26 5PH