Pond Extension and Liner Installation at London Luton Airport

The Challenge

This scheme required the excavation and extension of existing airport ponds and lagoons, together with concrete outlet base works, breakout of existing concrete, and the installation of a new geomembrane liner system to ponds A and B. The challenge was to deliver these works safely within a live operational environment, while protecting underground services, preparing the ponds to new design dimensions, and ensuring the finished liner system achieved the quality, containment, and long-term durability required.

Our Solution

We delivered a carefully controlled programme of excavation, breakout, concrete, and lining works designed to extend the ponds and provide a robust new containment system. Following service checks and safe excavation procedures, the existing pond extents were enlarged, concrete was broken out and removed where required, and new outlet bases were formed. We then prepared the subgrade, installed a 4000N geotextile underlay, and fitted a 1.5mm Exceliner PP geomembrane liner system with anchor trench detailing, welded seams, and full testing and quality assurance throughout.

Delivery & Techniques

The works began with pre-start safety controls and utility protection measures. Site-specific RAMS briefings were carried out each day, utility drawings were reviewed, and CAT and Genny surveys completed before excavation began. Where required, permits to dig were issued and trial holes hand dug around services, with no mechanical excavation carried out within 500mm of known utilities.

Excavation of the ponds was then completed using a 14 tonne excavator supported by a banksman. Existing pond areas were excavated to their new enlarged footprint, with spoil loaded into 3 tonne dumpers and taken either to stockpile or muck-away. All open excavations were barriered when unattended, with orange bunting used as edge protection.

As part of the extension works, existing lagoon concrete was broken out and removed using an inspected breaker attachment. Concrete was reduced into manageable sections and taken by dumper to a designated storage point, with appropriate eye and ear protection in place throughout the operation.

Concrete outlet base works were then completed by excavating to formation level, installing shuttering, compacting the sub-base, and pouring and vibrating the concrete to the required finish. The bases were allowed to cure before being prepared for the precast outlet units.

Before lining works could begin, the pond subgrade was trimmed and compacted to provide a suitable formation. Stones, roots, and debris greater than 10mm were removed, standing water cleared, and the surface approved through engineer and QA checks before progressing.

A 4000N geotextile underlay was then installed across the prepared formation. The material was laid wrinkle-free, with overlaps maintained at 300mm on flat areas and 500mm on slopes. Temporary anchoring was achieved using sandbags only, and any damaged sections were patched with the required overlap.

The main lining works involved the installation of a 1.5mm Exceliner PP geomembrane. Panels were carefully unrolled over the geotextile, allowed time to relax, and aligned to reduce seam numbers before being secured into anchor trenches. Sandbag ballast was used temporarily until permanent fixing was completed.

A strong QA process supported the final stage of the works. Welding was carried out using hot wedge and hot air techniques, with trial welds completed at the start of each shift. Minimum seam overlaps of 100mm were maintained, with dual track fusion welds used where possible. Air channel testing and vacuum box testing were undertaken as required, while any defects were repaired using extrusion welding or patched beyond the damaged area before being re-tested and recorded.

Outcomes & Benefits

The completed scheme extended the existing ponds to their new design dimensions and delivered a fully installed, tested, and quality-assured liner system to improve containment and long-term performance. By combining careful excavation, robust subgrade preparation, geotextile protection, and a fully welded geomembrane installation, the works provided a durable solution suited to the operational demands of the site. The structured QA and testing regime also helped ensure confidence in the integrity of the finished system.

Need help with Something Similar?

Leave your details here and we’ll get back to you as soon as possible. Alternatively, feel free to call us, drop an email or swing by the office any time.

08448 400 401

info@ecovigour.com

Hardwick Farm Five Lanes, Caerwent, Newport, Monmouthshire, NP26 5PH