Projects

Reptile Exclusion Fence Removal & Reinstatement – Rassau

The Challenge

EcoVigour had previously installed reptile exclusion fencing across a development site at Rassau, but the development was subsequently postponed and the temporary fencing remained in place for longer than originally anticipated. Exposure to weather and the passage of time had caused sections of the barrier to deteriorate, creating a risk that loose fencing material could enter nearby waterways or be carried onto local roads. The site itself presented difficult working conditions, with undulating ground left by earlier destructive investigation works making access and movement across the area more demanding. Although most of the redundant fencing needed to be removed, a 100 m section along the boundary with existing woodland still had to function as an exclusion barrier. The works therefore required selective removal, controlled disposal and targeted reinstatement rather than a straightforward clearance operation. Rassau Job Details

Our Solution

EcoVigour planned the works around two distinct requirements: remove redundant fencing across the majority of the site, while retaining and restoring the 100 m woodland-boundary section. Removing the deteriorated material reduced the potential for loose membrane to migrate beyond the site into roads or waterways and left the wider development area clear for future works. At the woodland edge, the existing barrier was repaired rather than removed so that ecological separation was maintained where it was still required. The approach allowed the team to deal with the immediate condition of the temporary fencing without unnecessarily replacing sections that no longer served a purpose. Once the ecological fencing works were complete, site security and associated barriers were reinstated so the area could be left secure and ready for future development. Rassau Job Details

Delivery & Techniques

The majority of the reptile fencing was dismantled and removed over two days, with the team working systematically across the uneven and disturbed site to recover the deteriorated membrane and associated fencing materials. The undulating terrain required careful manual working and movement of materials, particularly where previous intrusive investigations had left irregular ground conditions. Along the woodland boundary, approximately 100 m of fencing was repaired during a further day of work, reinstating the continuity and integrity of the exclusion barrier. The photographs show the fencing running through established vegetation and alongside woodland, illustrating the constrained conditions in which the retained section had to be accessed and repaired. The three-day delivery demonstrates EcoVigour’s ability to return to previously installed ecological mitigation, assess what remains necessary and carry out removal, repair and reinstatement as a single managed operation.

Outcomes & Benefits

EcoVigour removed and disposed of the redundant reptile fencing across the majority of the site, reducing the risk of deteriorating membrane being dispersed into local roads or waterways. The 100 m section bordering the existing woodland was repaired and left as a continuous barrier, maintaining the ecological function required at that boundary. Removal works were completed in two days, with the woodland-boundary repairs completed in a further day. Site security and barriers were then reinstated, leaving the area secure and prepared for the development programme to resume in the future. The project highlights EcoVigour’s ability to provide ongoing management of ecological mitigation measures, using experienced directly employed teams to adapt existing installations as site programmes and environmental requirements change.

Need help with Something Similar?

Leave your details here and we’ll get back to you as soon as possible. Alternatively, feel free to call us, drop an email or swing by the office any time.

08448 400 401

info@ecovigour.com

Hardwick Farm Five Lanes, Caerwent, Newport, Monmouthshire, NP26 5PH